Construction (Design and Management) Regulations 2015 advert image shown if present

Image shown for entry if relevant and present

These set are requirements for managing health, safety and welfare of individuals involved in construction projects. There are 5 main parts to the regulations:
• Part 1: Introduction; includes definitions;
• Part 2: Client duties; including Regulation 4. (1) "A client must make suitable arrangements for managing a project, including the allocation of sufficient time and other resources."
Regulation 6 identifies the time period and resource input for which the construction work would need to be notified to the HSE, "A project is notifiable if the construction work on a construction site is scheduled to"
(a) last longer than 30 working days and have more than 20 workers working simultaneously at any point in the project; or
(b) exceed 500 person days."